High-speed route Berlin-Munich

20.04.2018

25 years for four hours.

Over ten billion euros in construction costs, 25 years of planning and construction time: With the opening of Europe's largest and most expensive rail project, the Berlin-Munich high-speed line, Germany has been moving closer together since the end of last year. Thanks to a record travel time of just under four hours, from city centre to city centre, Deutsche Bahn wants to inspire travellers and encourage them to change from airplanes to trains.

High-speed route Berlin-Munich

Germany's most modern high-speed line was officially opened on 8 December 2017 with two special trains travelling and a major ceremony in Berlin in the presence of Federal Chancellor Angela Merkel, Federal Minister Christian Schmidt and several heads of state governments. Exactly 623 kilometres (via Halle) and 652 kilometres (via Leipzig) lie between the main stations of the German capital and the Bavarian metropolis. The ICE Sprinter, which stops three times a day on its way only in Halle, Erfurt and Nuremberg, shortens the travel time by a third from six hours to 3:55 hours. By way of comparison, the regular ICE can cover the distance in 4:30 hours.

 

Closing the gap in the European high-speed rail network

With a top speed of up to 300 km/h, the ICEs are on the move on sections of the newly built sections. At the heart of the new section that has now gone into operation, a nearly 110 kilometer long section through Thuringia, 22 tunnels and 27 viaducts were built. In addition to the national advantages, this high-speed line also brings Europe's North and South a little closer: it is an important component of the Trans-European Transport Networks (TEN-T) and, thanks to a common train control system, will make it possible in future to travel across national borders without changing railcars and without intermediate stops.

Milestones for Max Bögl

Together with the new Nuremberg-Ingolstadt-Munich line, the transport project German Unity No. 8 (VDE 8) with the new construction and extension of the lines between Nuremberg, Erfurt, Halle, Leipzig and Berlin is a project of superlatives. In 1991, after the reunification of Germany, the Federal Government decided that the new turbo line should sustainably improve the rail connections for passenger and freight traffic. The Max Bögl Group also played a major role in the implementation of this infrastructure measure, providing difficult engineering, tunneling and civil engineering services for the following sections:

NBS Nürnberg-Ingolstadt, Los Nord (35 km) between Feucht and Greding:

  • Turnkey construction of the line section up to OK Rail incl.
  • Göggelsbuch tunnel (2,287 m) and open construction (1,330 m)
  • Construction of various earthworks and bridges
  • Ballastless track system Bögl

news 2018 schnellfahrstrecke berlin muenchen 02 max boegl

NBS Ebensfeld–Erfurt (107 km):

  • Tunnels: Finnetunnel (6,886 m), Silberberg (7,391 m), Brandkopf (1,494 m) and Lohmeberg (688 m)
  • Railway bridges over the Wohlrose valley and Schobsetal

news 2018 schnellfahrstrecke berlin muenchen 03 max boegl

NBS Ebensfeld-Erfurt, Erfurt-Ilmenau section (32.5 km):

  • Permanent way in slab track Bögl
  • Noise barriers system Bögl

news 2018 schnellfahrstrecke berlin muenchen 04 max boegl

NBS Nuremberg-Ebensfeld (infrastructure measures Bubenreuth)

  • Earthworks, substructure: 352,220 m³
  • Drainage: 8,124 m
  • Diffusers: 305 m
  • shafts: 261 pieces up to max. 8 m depth
  • Provisional platforms: 1,200 m²
  • Overpasses: 13,000 m³ concrete, 10,000 m drilled piles, 7,000 m² sheet piles

Modulair systeem

Al tijdens de objectplanning kan de Max Bögl-groep middels de hybride spoorbrug Bögl al een deel van de oplossing zijn. Ontworpen voor één- en tweesporige spoorbruggen met spanwijdten tot 15 meter en een lage bouwhoogte verenigt de hybride bouwmethode van spoorbruggen de klassieke voordelen van de materialen staal en beton. Door industriële fabricage in de fabriek kunnen de afzonderlijke systeembouwelementen worden geprefabriceerd, in een magazijn worden opgeslagen en ter plaatse in een zeer korte bouwperiode tot verschillende individuele bouwwerken worden samengevoegd.

Modulair systeem

Voordelen

  • Gesegmenteerd systeem: transport over weg of per spoor
  • Industriële prefabricage: perfecte kwaliteit en precieze bouwelementen
  • Gestandaardiseerde modules, productie en bouwmethode: gecontroleerd productieproces, korte bouwperiode, levering en montage just in time
  • Naleving van de regels voor de bovenbouw van de spoorweg: eenvoudig onderhoud en herstel
  • Op BIM gebaseerde processen: efficiënt gebruik van de digitale waardeketen gedurende de gehele levenscyclus van het gehele bouwwerk
  • Productie en montage ook door licentiepartners
  • Onderhoudsarm concept
Voordelen

Video

Brochure

Brochure

Hybride Railway Bridge Bögl

This website uses cookies. By using our website, you consent to the use of cookies. Learn more ...