General renovation of Munich grammar schools

13.06.2019

Venerable, but in need of restoration.

The growing population, full-day care and the reintroduction of the G9 at the grammar schools prompted the City of Munich to launch an extensive expansion programme until 2030 as part of the school construction offensive. In addition to new buildings of various school types, educational institutions must also be repaired and expanded.

General renovation of Munich grammar schools

 

Close to Münchner Freiheit in the Schwabing district, the state capital is planning the general overhaul and expansion of the Oskar-von-Miller-Gymnasium and the Maximiliansgymnasium. Both were built before World War I and share a horseshoe-shaped building complex. After the Second World War, the venerable school building had to be rebuilt and comprehensively renovated at the end of the 1970s.

 

Building in historical ambience

While preserving the historical building fabric, the technical building equipment and the entire static load-bearing system of the listed existing building will be renewed over the next four years. The challenges include the replacement of ceilings, the installation of a new roof construction and the strengthening of the foundation by underpinning. In addition, the inner courtyard will be put to maximum use by installing an underground gymnasium and an extension building as a specialist class wing.

 

news 2019 sanierung muenchen 02 max boegl
Photo: Michael Stibitz

 

Complex shoring works

As technical leader in Arge, the Max Bögl Group was commissioned with extensive special civil engineering, drainage and earthworks. The main trades are jet grouting and large bored pile work. A back-anchored excavation pit with bracing base in the former gymnasium is being constructed by means of jet blasting for the new construction of an underground ventilation centre. This technology will also be used to underpin the strip foundations of the building wings and the head structures of both grammar schools. The new gymnasium and extension buildings will be constructed in excavation pits surrounded by simply back-anchored, overlapping pile walls. The existing groundwater levels, in conjunction with the depth of the gymnasium, require a lift protection with micropiles and a lowering of the groundwater level.

 

Three-layer excavation pit

Progressive explosive ordnance soundings, additional temporary steel girder structures with wood infill, low-pressure injection work and various steel girder frames are to be integrated into the work process. The special civil engineering works are supplemented by the excavation of the three-layer subsoil from filling, quaternary gravel as well as tertiary clays/slides and sands. After thorough analysis, the excavated material is sent to a qualified, proven disposal facility. The construction period for the complex remediation work extends from September 2018 to November 2020 - with a core construction period between October 2018 and May 2020.

 

Lean management is voor Max Bögl meer dan alleen maar een methode. Het is namelijk ons doel onze bedrijfsfilosofie blijvend te veranderen en een lerende organisatie met een lean-cultuur te creëren. In het kader van deze filosofie worden handelingsprincipes, zoals veranderings-, waarden- en foutencultuur verondersteld en ook geaccepteerd. De lean-principes zijn een hulpmiddel op onze weg naar een slank bouwbedrijf. De implementatie van de lean principes wordt uitgevoerd door dagelijks gebruik van de methoden en instrumenten door onze medewerkers.

Een beslissende factor op weg naar een slank bouwbedrijf zijn de medewerkers van de groep omdat zij als experts op hun werkplek een belangrijke rol bij de verandering vervullen. Om ze op de komende veranderingen voor te bereiden en hun de noodzakelijke kennis over te dragen werd de maxlean Academie opgericht. Doel is om met een vier-fasen opleidingsconcept onze collega's met de voor hen noodzakelijke knowhow toe te rusten. Ze worden door scholingen en door coaching ter plekke ondersteund om zo de lean-cultuur te leren kennen en die in hun dagelijkse werk toe te passen. De scholingen worden door simulaties ondersteund om zo de geleerde theorie aan de hand van praktische voorbeelden te intensiveren. Hierbij is de leerinhoud en het praktijkgedeelte afgestemd op de taakvelden van onze collega's om zo de praktische toepassing in het alledaagse werk te vergemakkelijken. De praktische toepassing en coaching ter plekke vinden plaats door de opgebouwde lean-structuur op de betreffende vakgebieden.

maxlean beperkt zich niet alleen tot één sector van ons bedrijf. Integendeel, Lean moet als uniforme aanpak worden gezien, waarbij aan onze hele keten waarde wordt toegevoegd. Binnen de Max Bögl -groep zien we lean management niet als begrensd, maar geïntegreerd in onze algehele strategie ‚Fortschritt 4.0‘. Daarbij kijken we zowel naar de productie en de bouwplaats maar ook naar de logistiek en administratieve disciplines om onze klanten de gevraagde diensten te verlenen.

This website uses cookies. By using our website, you consent to the use of cookies. Learn more ...