First use of slab track Bögl in Israel

15.11.2018

Highspeed between Tel Aviv and Jerusalem:

In 2001, Israel began building a fast rail link between the metropolises of Tel Aviv and Jerusalem. With the commissioning of the electrified high-speed railway line, the journey time, which on the previous historic railway route is around one and a half hours, will be reduced to one third.

First use of slab track Bögl in Israel

 

In 2015, the Israeli Railways decided to implement the FFB - Bögl ballastless track system on a section of around 23 km in length. As a further milestone for the overall completion, the superstructure work could now be completed and accepted in September 2018.

 

 

In addition to the existing single-track Jaffa-Jerusalem railway line, the country's largest infrastructure project is approaching completion after construction begins in 2001. The new double-track electrified railway line runs from Tel Aviv via Ben Gurion International Airport to Jerusalem in 30 minutes. The northern part of the approximately 56 km long line runs in tunnels and over bridges due to the mountainous topography existing there. These individual structures are among the longest and highest viaducts or longest and deepest tunnels in the country. This section with a length of around 23 km, including the new underground station in Jerusalem, was equipped with the Bögl ballastless track system. The southern section to Tel-Aviv, in which the Max Bögl Group was not involved, was constructed conventionally as a ballasted track.

 

The FFB superstructure system was originally developed and approved for railway lines with a design speed of up to 350 km/h. The FFB system was designed as a conventional ballasted superstructure with a maximum design speed of up to 350 km/h. The FFB system was originally developed and approved for railway lines with a design speed of up to 350 km/h. Although the trains on the new line should only reach speeds of up to 160 km/h, the Israeli Railways decided to build the Bögl slab track due to many other advantages. Durability, freedom from maintenance, availability, safety and driving comfort were the decisive criteria for this forward-looking decision. The contract for the production and installation of the FF Bögl system was awarded to the Max Bögl group of companies together with the Israeli company Electra Ltd. as a long-standing partner. In the course of this major project, a production facility for tunnel segments for the production of track supporting slabs near the line was converted by the end of 2015. The entire production technology, such as grinding machines and formwork, was transported to Israel by ship. After a subsequent two-month trial operation, series production of the approximately 7,000 pre-stressed prefabricated panels started in March 2016.

 

Once the Israeli partner had established the conditions for installation, the Bögl slab track was laid in several sections between October 2016 and July 2018. After completion of the rail assembly and successful acceptance of the ballastless track, this already electrified section was inaugurated in September by representatives of the Israeli government and the railways. Quality, track position and ride comfort fully met the expectations of the client. At present, only the section equipped with the Bögl ballastless track system is used by electric locomotives. The electrification of the rest of the line is still ongoing.

Contact

Rebekka Forchheimer
Deputy Head of Public Relations
Phone: +49 9181 909-10714
E-Mail: rforchheimer@max-boegl.de

„BIM is beslist geen modetrend, maar een nieuwe werkmethode voor ons bedrijf en de gehele bouwindustrie, waarbij we als pionier voorop willen lopen.“

Met deze woorden benadrukt Stefan Bögl welk vooruitstrevend doel de groep voor ogen heeft. Om met dit ontwikkelingsproces steeds op koers te blijven is een voortdurende uitwisseling nodig tussen alle divisies – BIM is en wordt hierbij een gemeenschappelijk instrument voor een coöperatief, digitaal samenwerken en effent voor ons bedrijf de weg als een solide strategie voor „industrieel bouwen“.

Daaronder verstaan we de rationalisering van arbeidsprocessen, kostenefficiency, een grotere productiviteit en kwaliteit. We willen dit toepassen door middel van speciale methoden, zoals de prefabricage van bouwcomponenten (prefab-productie), standaardisering van bouwelementen bij een gelijktijdige flexibiliteit in de vormgeving (maxmodul) en vooral door het optimaliseren van onze planning- en productieprocessen. Belangrijke basis voor bovengenoemde methoden is de interactie tussen onze BIM-methodiek en lean management.

BIM – een werkmethode

Een met BIM uitgevoerd projectproces wint significant aan transparantie. Daardoor wordt de kwaliteit van ons werk weer verbeterd. Kostenreductie en leverstiptheid worden vergroot doordat fouten in de planning en werkvoorbereiding tot een minimum worden teruggebracht. Op deze manier kan de afwikkeling van alle projecten niet alleen exact worden vormgegeven, maar ook gecontroleerd worden aangestuurd. BIM is daarom meer dan alleen maar een intelligent 3D-model. Het is een werkmethodiek die mensen in het kader van de digitalisering via moderne technologieën met elkaar verbindt. Hoe meer gebruikers deze methode consequent in hun dagelijkse werk integreren en actief gebruiken, des te meer wordt voor alle betrokkenen het werk verlicht.

BIM – een werkmethode
blank

"Due to the GPS-supported control of the excavator, we can carry out the
often time-consuming earthworks on the construction site very precisely."

Rene Kuchenbaur, Supply and Disposal

blank

"The shuttering laser is a great relief for my work.
I don't have to measure anything by hand anymore.
That this is a BIM application,
but I wasn't aware of it until now."

Denis Buchner, Formwork preparation FTW Bachhausen

blank

"Given the size of today's construction projects we're handling, it would be difficult to work without a centralized overview model."

Lukas Palotz, Calculation building construction