General renovation of the Alz canal

13.10.2017

Fit for another 100 years.

Without him, there would be neither Wacker Chemie AG in Burghausen nor any other industry in today's Bavarian chemical triangle east of Munich. But since its completion in 1922, the Alzkanal, the lifeline of the district of Altötting, has grown old.

General renovation of the Alz canal

 

The first general overhaul after almost 100 years of operation was therefore a top priority for Wacker - and posed enormous challenges for those involved in this major project.

news 2017 generalsanierung alzkanal 02 max boegl

Built between 1915 and 1922, the Alzkanal still supplies electricity, emergency power and cooling water to the main plant of the global chemicals group. To ensure that this remains the case in the future, the 16.7 kilometer long channel was extensively renewed in several sections and the structural substance of eleven structures and two tunnels renovated. Over 400 skilled workers and numerous special equipment were in continuous use to cope with the demanding infrastructure measures. In the course of the rehabilitation of 1.8 kilometres of channels, 0.9 kilometres of tunnels and three canal structures in lots 8-13, the client Wacker commissioned the rehabilitation specialists from Max Bögl in a joint venture.

Repair with state-of-the-art techniques

After preparatory measures had been taken in advance, the canal could be backed up as planned within three days, so that by the end of August 2016 there was "freedom to build" within the channel. In the now completely empty sewer, around 40,000 square metres of concrete were cleaned over the entire length of the stretch using high-pressure rinsing vehicles. After the subsequent inventory and damage survey, partly using the latest laser scanning technology, the rehabilitation work could begin. To this end, the joints, which had become old, were repaired over a total length of around 5,000 metres and sealed with a new grout. Local damage to the trapezoidal channel was repaired as required.

news 2017 generalsanierung alzkanal 03 max boegl

In the area of the structures, the old coating and the damaged concrete also had to be removed using high-pressure water jets or special attachment milling machines. These surfaces were then reprofiled with shotcrete/mortar and provided with a new coating. In addition to the surface repair, a large number of cracks, defects and joints had to be worked on. At peak times, up to 140 skilled workers, accommodated in a residential camp set up especially for the construction project, were employed 24 hours a day, seven days a week in multi-shift operation. The core measures were completed on schedule after a construction period of only seven weeks.

news 2017 generalsanierung alzkanal 04 max boegl

Cavity backfilling with low pressure injection

In the course of the 20th shutdown in the history of the canal, two tunnels, each 206 and 688 metres long, had to be rehabilitated near Burgkirchen. Both tunnels were built in Belgian style at the beginning of the 20th century. Over the decades, however, parts of the wooden formwork remaining in the mountain began to rot behind the tunnel wall. Numerous cavities were created, which now had to be filled. For this purpose, the damaged areas were localised with a georadar and corresponding boreholes were drilled. A cement slurry was then injected into the approximately 5,000 boreholes using a low-pressure injection process, thus permanently filling the cavities. In total, almost 1.6 million litres of cement bentonite suspension had to be injected into both tunnels with several injection pumps running in parallel.

Systematisiert im Bau. Vielfältig in der Gestaltung.

 

Effizienz zieht sich bei uns durch alle Projektphasen des systematisierten Industriebaus. Für Gewerbeimmobilien hat die Firmengruppe Max Bögl ein System entwickelt, das Zeit und Kosten spart und gleichzeitig ausreichend Freiraum für individuelle Anforderungen lässt. Die Konstruktion der Hallenbauten erfolgt mittels einer flexiblen Zusammensetzung individuell angepasster Bauteile. Die jeweiligen Bestandteile – wie Stützen, Unterzüge oder Dachbinder – entstammen sozusagen einem Baukasten-System, passen stets präzise ineinander und lassen sich beliebig miteinander verbinden und erweitern. Auch die Realisierung mehrstöckiger Immobilien ist damit kein Problem.

Zudem können wir dank dieser Methode Bauteile in höchster Präzision und Qualität fertigen. Alle Arbeitsabläufe werden stets sorgfältig und zuverlässig geplant, sodass jeder Handgriff zur passenden Zeit und an der richtigen Stelle vorgenommen wird. Diese Optimierung ermöglicht einen nachhaltigen Bauprozess, da die benötigte Energie für die Produktion bestmöglich eingesetzt wird.

ln der gewinnbringenden Anwendung des digitalen Bauens besitzt Max Bögl die Marktführerschaft in Deutschland und ist dafür bereits mehrfach ausgezeichnet worden. Schließlich erreichen wir umfassende Effizienz und Qualität durch klare und eindeutige Grundsätze, die wir bei Max Bögl im systematisierten lndustriebau anwenden.

Systematisiert im Bau. Vielfältig in der Gestaltung.

Ganzheitliche Lösungen

Neben der Ausführung der reinen Bauleistung bietet Max Bögl auch die Beratung und Planung über alle Projektphasen hinweg an. So können Sie Ihre Halle gemeinsam mit unseren Experten individuell konfigurieren und an Ihre speziellen Bedürfnisse anpassen.

  • Bedarfsanalyse
  • Entwurfsplanung
  • Detailplanung
  • Angebot
  • Vertragsunterzeichnung
  • Baustart
  • Fertigstellung

 

Ganzheitliche Lösungen

Vorteile des Hallensystems Bögl

Unsere Referenzen – Ihre Inspiration

blank

Kiekebusch

Logistikzentrum Septima

mehr Infos
blank

Kelsterbach

Logistikzentrum Immogate

mehr Infos
blank

Oelde

Logistikzentrum Gazeley

mehr Infos
blank

Mannheim

Schwerlastverladehalle Kübler

mehr Infos
blank

Gera

Produktionshalle Stahlo

mehr Infos
blank

Poing

Logistikzentrum Schustermann & Borenstein

mehr Infos

Diese Webseite verwendet Cookies. Indem Sie unsere Webseite nutzen, stimmen Sie der Verwendung von Cookies zu. Mehr erfahren ...