News
Work on the Alb descent tunnel making progress
12.04.2016
Half time without a break at the ICE tunnel construction in Ulm. Of the 5.9 kilometres that the Alb descent tunnel with its two individual tubes will have in length, five kilometres have already been excavated using combined excavator and blast tunnelling.