High-speed route Berlin-Munich

20.04.2018

25 years for four hours.

Over ten billion euros in construction costs, 25 years of planning and construction time: With the opening of Europe's largest and most expensive rail project, the Berlin-Munich high-speed line, Germany has been moving closer together since the end of last year. Thanks to a record travel time of just under four hours, from city centre to city centre, Deutsche Bahn wants to inspire travellers and encourage them to change from airplanes to trains.

High-speed route Berlin-Munich

Germany's most modern high-speed line was officially opened on 8 December 2017 with two special trains travelling and a major ceremony in Berlin in the presence of Federal Chancellor Angela Merkel, Federal Minister Christian Schmidt and several heads of state governments. Exactly 623 kilometres (via Halle) and 652 kilometres (via Leipzig) lie between the main stations of the German capital and the Bavarian metropolis. The ICE Sprinter, which stops three times a day on its way only in Halle, Erfurt and Nuremberg, shortens the travel time by a third from six hours to 3:55 hours. By way of comparison, the regular ICE can cover the distance in 4:30 hours.

 

Closing the gap in the European high-speed rail network

With a top speed of up to 300 km/h, the ICEs are on the move on sections of the newly built sections. At the heart of the new section that has now gone into operation, a nearly 110 kilometer long section through Thuringia, 22 tunnels and 27 viaducts were built. In addition to the national advantages, this high-speed line also brings Europe's North and South a little closer: it is an important component of the Trans-European Transport Networks (TEN-T) and, thanks to a common train control system, will make it possible in future to travel across national borders without changing railcars and without intermediate stops.

Milestones for Max Bögl

Together with the new Nuremberg-Ingolstadt-Munich line, the transport project German Unity No. 8 (VDE 8) with the new construction and extension of the lines between Nuremberg, Erfurt, Halle, Leipzig and Berlin is a project of superlatives. In 1991, after the reunification of Germany, the Federal Government decided that the new turbo line should sustainably improve the rail connections for passenger and freight traffic. The Max Bögl Group also played a major role in the implementation of this infrastructure measure, providing difficult engineering, tunneling and civil engineering services for the following sections:

NBS Nürnberg-Ingolstadt, Los Nord (35 km) between Feucht and Greding:

  • Turnkey construction of the line section up to OK Rail incl.
  • Göggelsbuch tunnel (2,287 m) and open construction (1,330 m)
  • Construction of various earthworks and bridges
  • Ballastless track system Bögl

news 2018 schnellfahrstrecke berlin muenchen 02 max boegl

NBS Ebensfeld–Erfurt (107 km):

  • Tunnels: Finnetunnel (6,886 m), Silberberg (7,391 m), Brandkopf (1,494 m) and Lohmeberg (688 m)
  • Railway bridges over the Wohlrose valley and Schobsetal

news 2018 schnellfahrstrecke berlin muenchen 03 max boegl

NBS Ebensfeld-Erfurt, Erfurt-Ilmenau section (32.5 km):

  • Permanent way in slab track Bögl
  • Noise barriers system Bögl

news 2018 schnellfahrstrecke berlin muenchen 04 max boegl

NBS Nuremberg-Ebensfeld (infrastructure measures Bubenreuth)

  • Earthworks, substructure: 352,220 m³
  • Drainage: 8,124 m
  • Diffusers: 305 m
  • shafts: 261 pieces up to max. 8 m depth
  • Provisional platforms: 1,200 m²
  • Overpasses: 13,000 m³ concrete, 10,000 m drilled piles, 7,000 m² sheet piles

Verfahrensbeschreibung (Stahlschutzrohr)

Dieses Verfahren wird in 3 Phasen folgendermaßen durchgeführt:

Phase 1: Gesteuerte Pilotbohrung

 

Gesteuerte Pilotrohrvortriebe werden mit Hilfe von Pilotrohren (Außendurchmesser 114 mm) mit optischer Gasse, Steuerkopf, Theodolit mit CCD-Kamera und Monitor in verdrängungsfähigen Böden ausgeführt. Das Pilotrohr wird durch den Boden bis in die Zielgrube gepresst, wobei Richtung und Neigung überwacht werden. Durch die abgeschrägte Fläche des Steuerkopfes lässt sich die Bohrung in alle Richtungen steuern und so Abweichungen von der Bohrtrasse verhindern.

Phase 1: Gesteuerte Pilotbohrung

Phase 2: Aufweitungsbohrung

 

  1. Das Pilotgestänge und das Stahlrohr werden mittels Aufweitstufe (aktiv oder passiv) miteinander verbunden.
  2. Das Pressrohr wird hydraulisch vorgepresst, gleichzeitig wird mit den Förderschnecken der sich in das Pressrohr schiebende Boden herausgebohrt.
  3. Das Pilotgestänge führt das Stahlrohr in der exakt vorgegebenen Richtung.
  4. Das Pilotgestänge schiebt sich während des Aufweitvorganges in die Zielgrube, wo es auseinandergeschraubt und abgebaut wird.

 

In locker bis mitteldicht gelagerten Sand- und Kiesböden verwendet man eine passive Aufweitstufe. Dabei läuft der Bohrkopf zurückgesetzt im Schutze des Stahlrohres. Bei dichter Bodenlagerung ist es nicht mehr möglich, die Stege der Passiven Aufweitstufe in den Boden zu drücken. Man setzt daher eine Aktive Aufweitstufe ein, bei der eine Schürfscheibe unmittelbar vor dem Stahlrohr läuft. Die Öffnungen der Schürfscheibe kann man je nach zu erwartendem Steindurchmesser verkleinern, um so die Gefahr drohender Bodeneinbrüche zu verringern. Bei Vortrieben im Grundwasser kommen sogenannte „Grundwasserschleusen“ zum Einsatz.

 

Phase 2: Aufweitungsbohrung

Phase 3: Nachschub der Kanal-Vortriebsrohre

 

Einbau von einem oder mehreren Medienrohre als Bündel in das Stahlschutzohr auf Gleitkufen. Auf Kundenwunsch können wir den Ringraum zwischen den Rohren auch gerne verdämmen.

 

Phase 3: Nachschub der Kanal-Vortriebsrohre

Phase 3: Nachschub der Kanal-Vortriebsrohre

 

Man verbindet das Kanal-Vortriebsrohr in der Startgrube mit dem Stahl-Pressrohr. Der gesamte Strang wird vorgepresst. Das Stahl-Pressrohr schiebt sich hierbei in die Zielgrube, wo es getrennt und ausgebaut wird. Am Ende des Vorganges hat man das Stahl-Pressrohr durch das Kanal-Vortriebsrohr ausgetauscht.

 

Phase 3: Nachschub der Kanal-Vortriebsrohre