Vonovia completes modular new building in Bayreuth

22.02.2018

After around four months of construction Vonovia has completed the new residential building "Am schwarzen Steg" in Bayreuth. Among the guests of the symbolic key handover was the Lord Mayor of Bayreuth, Brigitte Merk-Erbe. The modular construction of the house with 20 new apartments had begun in October 2017, and the topping-out ceremony was already celebrated in November.

  • 20 apartments with around 1,300 square meters of living space
  • round four months Construction time
  • First collaboration with Max Bögl Modul AG
Vonovia completes modular new building in Bayreuth

 

The investment volume amounted to around 2.5 million euros. The apartments are between 40 and 140 square metres in size and the total living space is around 1,300 square metres. "This makes the apartments just as suitable for senior citizens as for families," explained Klaus Freiberg, member of the Executive Board of Vonovia SE, on the occasion of the completion. "In addition to the short construction period, the modular construction method has another decisive advantage: the construction costs are lower and the apartments affordable. The costs are around 30 percent lower than for conventional construction. The average rent for Am schwarzen Steg will be around 9.50 euros per square metre. All apartments have either a balcony or terrace and are barrier-free. Two are also wheelchair accessible. An additional 31 car and 16 bicycle parking spaces have been created on the property for tenants. Mayor Brigitte Merk-Erbe emphasized the importance of the modular new building: "Affordable apartments close to the city centre are what we need on the Bayreuth housing market, which is in great demand. "Modular construction" means that the four-storey building consists of standardized elements that were transported to the construction site by low-loader. The reinforced concrete modules were already prefabricated with windows, doors and floor coverings in the factory, so that the assembly time of the modules after the earthworks was only ten days. The general contractor for the project and Vonovia's partner for the first time is the Max Bögl Group. "The entire maxmodul team is very pleased to be able to hand over a future-oriented residential building to our partner Vonovia today with the symbolic key handover of our joint pilot project with regard to quality, economy and adherence to schedules. With the innovative, modular construction system "maxmodul", we want to make affordable living space with high social and ecological quality available in Germany in the shortest possible time - without compromising on architecture," explained Markus Richthammer, Board Member for Industry and responsible for the product "maxmodul" at Max Bögl Modul AG. Most of the apartments have already been let and the first tenants will move in in March. Vonovia, Germany's leading housing company, manages around 18,000 apartments in Bavaria and around 100 apartments in Bayreuth. All further information inclusive film and photo photographs to the project:

 

Contact:

Jürgen Kotzbauer
Head of Public Relations
Phone: +49 9181-909-10712
Mail: jkotzbauer@max-boegl.de

Auf der maxlandkarte ist der komplette Prozess der Projektabwicklung von der Akquisephase bis zum Ende der Gewährleistungsphase abgebildet. Der Fokus liegt dabei auf den arbeitsvorbereitenden Tätigkeiten, um Fehler in der späteren Ausführung frühzeitig erkennen und vermeiden zu können und dadurch Kosten zu sparen und Qualität und Termine sicherzustellen. Durch Freigaben der Meilensteine von einer Phase zur nächsten minimieren wir das Risiko in der Projektabwicklung und verhindern, dass Kapazitäten falsch eingesetzt werden.

Typische Ergebnisse der standardisierten Projektabwicklung sind Effizienzsteigerungen in der Durchführung und Steuerung von komplexen Projekten sowie eine Reduzierung von Wiederholungen, Nacharbeiten und Umplanungen, wodurch sich die Projektgeschwindigkeit erhöht. Zusätzlich wird durch eine klare Verteilung von Aufgaben, Kompetenzen und Verantwortungen eine verbesserte Kontrolle sowie Transparenz trotz vieler Projektbeteiligter erreicht. Während die interdisziplinäre Ausgestaltung des Projektteams für ausreichendes und vielfältiges Expertenwissen sorgt, wird die gesamtheitliche Planung und Steuerung des Projektes durch die durchgängige Beteiligung der Prozessrolle Projektmanagement sichergestellt.

Durch eine dreistufige Gremienstruktur – bestehend aus dem Projektteam, dem Steuerkreis sowie dem Lenkungskreis – wird eine verbesserte Unterstützung der Projekte sowie die Herbeiführung schnellerer Entscheidungen ermöglicht. Aufgrund der Verlagerung der Entscheidungskompetenz auf die unteren Ebenen wird der Fokus auf wenige, wichtige Entscheidungen gelegt und auf diese Weise das Management entlastet.