High-speed route Berlin-Munich

20.04.2018

25 years for four hours.

Over ten billion euros in construction costs, 25 years of planning and construction time: With the opening of Europe's largest and most expensive rail project, the Berlin-Munich high-speed line, Germany has been moving closer together since the end of last year. Thanks to a record travel time of just under four hours, from city centre to city centre, Deutsche Bahn wants to inspire travellers and encourage them to change from airplanes to trains.

High-speed route Berlin-Munich

Germany's most modern high-speed line was officially opened on 8 December 2017 with two special trains travelling and a major ceremony in Berlin in the presence of Federal Chancellor Angela Merkel, Federal Minister Christian Schmidt and several heads of state governments. Exactly 623 kilometres (via Halle) and 652 kilometres (via Leipzig) lie between the main stations of the German capital and the Bavarian metropolis. The ICE Sprinter, which stops three times a day on its way only in Halle, Erfurt and Nuremberg, shortens the travel time by a third from six hours to 3:55 hours. By way of comparison, the regular ICE can cover the distance in 4:30 hours.

 

Closing the gap in the European high-speed rail network

With a top speed of up to 300 km/h, the ICEs are on the move on sections of the newly built sections. At the heart of the new section that has now gone into operation, a nearly 110 kilometer long section through Thuringia, 22 tunnels and 27 viaducts were built. In addition to the national advantages, this high-speed line also brings Europe's North and South a little closer: it is an important component of the Trans-European Transport Networks (TEN-T) and, thanks to a common train control system, will make it possible in future to travel across national borders without changing railcars and without intermediate stops.

Milestones for Max Bögl

Together with the new Nuremberg-Ingolstadt-Munich line, the transport project German Unity No. 8 (VDE 8) with the new construction and extension of the lines between Nuremberg, Erfurt, Halle, Leipzig and Berlin is a project of superlatives. In 1991, after the reunification of Germany, the Federal Government decided that the new turbo line should sustainably improve the rail connections for passenger and freight traffic. The Max Bögl Group also played a major role in the implementation of this infrastructure measure, providing difficult engineering, tunneling and civil engineering services for the following sections:

NBS Nürnberg-Ingolstadt, Los Nord (35 km) between Feucht and Greding:

  • Turnkey construction of the line section up to OK Rail incl.
  • Göggelsbuch tunnel (2,287 m) and open construction (1,330 m)
  • Construction of various earthworks and bridges
  • Ballastless track system Bögl

news 2018 schnellfahrstrecke berlin muenchen 02 max boegl

NBS Ebensfeld–Erfurt (107 km):

  • Tunnels: Finnetunnel (6,886 m), Silberberg (7,391 m), Brandkopf (1,494 m) and Lohmeberg (688 m)
  • Railway bridges over the Wohlrose valley and Schobsetal

news 2018 schnellfahrstrecke berlin muenchen 03 max boegl

NBS Ebensfeld-Erfurt, Erfurt-Ilmenau section (32.5 km):

  • Permanent way in slab track Bögl
  • Noise barriers system Bögl

news 2018 schnellfahrstrecke berlin muenchen 04 max boegl

NBS Nuremberg-Ebensfeld (infrastructure measures Bubenreuth)

  • Earthworks, substructure: 352,220 m³
  • Drainage: 8,124 m
  • Diffusers: 305 m
  • shafts: 261 pieces up to max. 8 m depth
  • Provisional platforms: 1,200 m²
  • Overpasses: 13,000 m³ concrete, 10,000 m drilled piles, 7,000 m² sheet piles

Lean Management ist für Max Bögl mehr als eine Methode. Denn Ziel ist es, die Unternehmensphilosophie nachhaltig zu verändern und eine lernende Organisation mit einer Lean-Kultur zu schaffen. Im Rahmen der Philosophie werden Verhaltensgrundsätze wie Veränderungs-, Werte- und Fehlerkultur bedingt und gefördert. Als Leitplanken auf unserem Weg zum schlanken Bauunternehmen dienen die Lean-Prinzipien. Die Verwirklichung der Lean-Prinzipien erfolgt durch die Methoden und Werkzeuge, die unseren Mitarbeitern als Handwerkszeug zur täglichen Umsetzung dienen.

Ein entscheidender Faktor auf dem Weg zum schlanken Bauunternehmen sind die Mitarbeiterinnen und Mitarbeiter der Firmengruppe, da sie als Experten an ihrem Arbeitsplatz eine wichtige Rolle zur Veränderung einnehmen. Um sie auf die kommenden Veränderungen vorzubereiten und ihnen die nötigen Kenntnisse zu vermitteln, wurde die maxlean Akademie gegründet. Ziel ist es, mit dem vierstufigen Schulungskonzept unsere Kollegen mit den für sie nötigen Inhalten auszubilden. Hierbei werden sie mit Schulungen, aber auch durch Coachings vor Ort unterstützt und sollen so die Lean-Kultur kennenlernen und in ihrer täglichen Arbeit anwenden. Die Schulungen werden mit Simulationen gestützt, um die gelernte Theorie anhand des praktischen Beispiels zu intensivieren. Hierbei sind die Lerninhalte wie auch der Praxisteil auf die Tätigkeitsfelder unserer Kollegen abgestimmt, um so den Übertrag in den Arbeitsalltag zu erleichtern. Die Umsetzung und das Coaching vor Ort erfolgen durch die aufgebaute Lean-Struktur in den jeweiligen Fachbereichen.

maxlean begrenzt sich nicht nur auf einen Bereich unseres Unternehmens. Ganz im Gegenteil, Lean ist als ganzheitlicher Ansatz zu verstehen, der unsere gesamte Wertschöpfungskette optimiert. Wir in der Firmengruppe Max Bögl sehen Lean Management nicht als begrenzt, sondern in unsere Gesamtstrategie Fortschritt 4.0 integriert. Hierbei betrachten wir sowohl die Produktion und die Baustelle als auch die Logistik und die administrativen Bereiche, um unseren Kunden die gewünschte Leistung zu bieten.

Diese Webseite verwendet Cookies. Indem Sie unsere Webseite nutzen, stimmen Sie der Verwendung von Cookies zu. Mehr erfahren ...