Tübbing delivery for the Filder Tunnel completed

14.08.2019

The Max Bögl Group delivers over 50,000 segments by rail.

Tübbing delivery for the Filder Tunnel completed

 

Since December 2014, the Max Bögl Group has regularly supplied the construction site of the Filder Tunnel with segments from the precast factory in Sengenthal by rail. Tubbings are high-precision precast concrete elements and are used for the construction of the inner shell of the tunnel. The Fildertunnel consists of two tubes, each 9.5 km long, and is divided into the Lower and Upper Fildertunnel sections. Depending on the construction phase, the segment rings have a wall thickness of 45 or 60 cm and weigh around 71 or 93 tonnes respectively. In total, the group produced over 7,300 rings, each consisting of seven individual segments.

 


Foto: Firmengruppe Max Bögl

 

After a total of 474 trains, the last Tübbing train will now be sent to Stuttgart on 14.08.2019. Thanks to the sustainable rail transport, 22,973 truck transports could be avoided, which would otherwise have been necessary. In total, almost 600,000 tons of segments were transported from the Sengenthal plant to the receiving station near Plochingen. There they were transferred by forklift from the wagon to the truck or to the interim storage facility and then delivered to the tunnel portal. The Fildertunnel is part of the major "Stuttgart 21" project and will connect Stuttgart Central Station with the Filder plain after completion. It is part of the new Wendlingen-Ulm line.

Contact

Jürgen Kotzbauer
Phone: +49 9181 909-10712 
E-Mail: jkotzbauer@max-boegl.de

Totalentreprenør på BaseCamp Lyngby, som vinder Årets Byggeri 2020

Totalentreprenør på BaseCamp Lyngby, som vinder Årets Byggeri 2020

18.12.2020

Max Bögl har i samspil med JFP stået som totalentreprenør for det spektakulære byggeri BaseCamp Lyngby, som snor sig elegant igennem det omkringliggende landskab.

Læs mere
Max Bögl og JFP afleverer gigantbyggeriet BaseCamp Lyngby til tiden

Max Bögl og JFP afleverer gigantbyggeriet BaseCamp Lyngby til tiden

07.09.2020

Max Bögl afleverede sammen med JFP gigantbyggeriet, BaseCamp Lyngby til tiden den 1. september. Med 41.150 m2 og coronakrise som del af byggeperioden, er det bemærkelsesværdigt.

Læs mere
Siemens Gamesa and Max Bögl Wind AG sign partnership agreement

Siemens Gamesa and Max Bögl Wind AG sign partnership agreement

24.06.2020

Increased profitability of wind power projects. Siemens Gamesa Renewable Energy, one of the world’s leading wind turbine manufacturers, and the German hybrid tower producer, Max Bögl Wind AG, have agreed …

Læs mere

This website uses cookies. By using our website, you consent to the use of cookies. Learn more ...