General renovation of the Alz canal

13.10.2017

Fit for another 100 years.

Without him, there would be neither Wacker Chemie AG in Burghausen nor any other industry in today's Bavarian chemical triangle east of Munich. But since its completion in 1922, the Alzkanal, the lifeline of the district of Altötting, has grown old.

General renovation of the Alz canal

 

The first general overhaul after almost 100 years of operation was therefore a top priority for Wacker - and posed enormous challenges for those involved in this major project.

news 2017 generalsanierung alzkanal 02 max boegl

Built between 1915 and 1922, the Alzkanal still supplies electricity, emergency power and cooling water to the main plant of the global chemicals group. To ensure that this remains the case in the future, the 16.7 kilometer long channel was extensively renewed in several sections and the structural substance of eleven structures and two tunnels renovated. Over 400 skilled workers and numerous special equipment were in continuous use to cope with the demanding infrastructure measures. In the course of the rehabilitation of 1.8 kilometres of channels, 0.9 kilometres of tunnels and three canal structures in lots 8-13, the client Wacker commissioned the rehabilitation specialists from Max Bögl in a joint venture.

Repair with state-of-the-art techniques

After preparatory measures had been taken in advance, the canal could be backed up as planned within three days, so that by the end of August 2016 there was "freedom to build" within the channel. In the now completely empty sewer, around 40,000 square metres of concrete were cleaned over the entire length of the stretch using high-pressure rinsing vehicles. After the subsequent inventory and damage survey, partly using the latest laser scanning technology, the rehabilitation work could begin. To this end, the joints, which had become old, were repaired over a total length of around 5,000 metres and sealed with a new grout. Local damage to the trapezoidal channel was repaired as required.

news 2017 generalsanierung alzkanal 03 max boegl

In the area of the structures, the old coating and the damaged concrete also had to be removed using high-pressure water jets or special attachment milling machines. These surfaces were then reprofiled with shotcrete/mortar and provided with a new coating. In addition to the surface repair, a large number of cracks, defects and joints had to be worked on. At peak times, up to 140 skilled workers, accommodated in a residential camp set up especially for the construction project, were employed 24 hours a day, seven days a week in multi-shift operation. The core measures were completed on schedule after a construction period of only seven weeks.

news 2017 generalsanierung alzkanal 04 max boegl

Cavity backfilling with low pressure injection

In the course of the 20th shutdown in the history of the canal, two tunnels, each 206 and 688 metres long, had to be rehabilitated near Burgkirchen. Both tunnels were built in Belgian style at the beginning of the 20th century. Over the decades, however, parts of the wooden formwork remaining in the mountain began to rot behind the tunnel wall. Numerous cavities were created, which now had to be filled. For this purpose, the damaged areas were localised with a georadar and corresponding boreholes were drilled. A cement slurry was then injected into the approximately 5,000 boreholes using a low-pressure injection process, thus permanently filling the cavities. In total, almost 1.6 million litres of cement bentonite suspension had to be injected into both tunnels with several injection pumps running in parallel.

Synergie w koncernie

Dla nas budowanie wartości zaczyna się już na samym początku: Zakłady firmowe zaopatrywane są w surowce z własnych żwirowni, piaskowni i kamieniołomów Max Bögl, dzięki czemu prefabrykaty betonowe produkowane są z zachowaniem najwyższych standardów jakościowych. Nasza flota, składająca się m.in. z ponad 300 ciężarówek, stanowi niezawodny łącznik pomiędzy zakładami a placami budowy. Ponadto, dzięki własnemu doświadczeniu w zakresie budownictwa podziemnego, możemy również sami świadczyć usługi infrastrukturalne – nawet na wymagających podłożach. Wraz z naszymi kolegami z działu „Energie odnawialne” zapewniamy Państwa nieruchomościom zrównoważone i wydajne wyposażenie budynków – aż po neutralność energetyczną.

Nasi klienci odczuwają wymierne korzyści dzięki krótkim trasom i minimalnej liczbie osób odpowiedzialnych – podczas całego projektu do Państwa dyspozycji pozostaje jedna i ta sama osoba kontaktowa.

Synergie w koncernie

Przyszłość budownictwa

Nieustanne kwestionowanie status quo, stały rozwój i optymalizacje to najważniejsze priorytety Grupy Max Bögl. Dlatego też z determinacją rozwijamy i udoskonalamy takie aspekty jak BIM, Lean oraz standaryzowane zarządzanie projektami, aby móc realizować projekty z najwyższą wydajnością i przejrzystością. Konsekwentne stosowanie metod BIM umożliwia m.in. weryfikowanie procesów budowlanych i wykrywanie kolizji już na etapie zakupu. Dzięki temu można na przykład sprawdzić, czy zaplanowana przestrzeń przy instalacji wentylacyjnej jest wystarczająca do przeprowadzenia wymiany filtra w późniejszym okresie eksploatacji.

Bezpieczeństwo pracy również odgrywa istotną rolę w optymalizacji naszych procesów przy pomocy narzędzi Lean. Jako osobny punkt w naszej specjalnie opracowanej matrycy maxpoint, kwestia ta jest codziennie szczegółowo omawiana i analizowana na placach budowy w dialogu ze wszystkimi uczestnikami procesu budowy. To szczególne wyczulenie naszych pracowników na kwestie bezpieczeństwa znajduje również odzwierciedlenie w liczbach. Przykładowo, centrum logistyczne o powierzchni 19 boisk piłkarskich zdołaliśmy wybudować w ciągu zaledwie 18 miesięcy – i to bez żadnego wypadku w ciągu około 500 000 godzin pracy.

Przyszłość budownictwa

This website uses cookies. By using our website, you consent to the use of cookies.